Swaggs21 House Build Thread
Neg. I couldn't bring myself to live in a double wide after owning 2 really nice houses.
Really glad work is being flexible though. If it wasn't for that, I would be about to blow up on the daily because of screw-ups.
I will have internet at the apartment tomorrow, which will make life much easier.
After today it should really start taking shape fast.
Really glad work is being flexible though. If it wasn't for that, I would be about to blow up on the daily because of screw-ups.
I will have internet at the apartment tomorrow, which will make life much easier.
After today it should really start taking shape fast.
Last edited by swaggs21; Jul 29, 2009 at 03:03 AM.
there is a walkout on the backside and there is also a lot of rescaping of the land. The front of the house (to the left side of the hole) will be brought up almost 3 feet with dirt and fill to get to the new grade once the walls are set. That is where most of the height missing is coming from.
No work today due to rain, even though I told them yesterday they needed to work late to make sure they stayed on schedule for Thursday. When I dropped by the property yesterday afternoon at 1430 there was no one in sight.
Now I am being told that the walls won't go in till Monday most likely, which makes me ol so happy.
Needless to say someone got yelled at this morning, because the contractor didn't even show up on the job, he called to see if it was raining.
No work today due to rain, even though I told them yesterday they needed to work late to make sure they stayed on schedule for Thursday. When I dropped by the property yesterday afternoon at 1430 there was no one in sight.
Now I am being told that the walls won't go in till Monday most likely, which makes me ol so happy.
Needless to say someone got yelled at this morning, because the contractor didn't even show up on the job, he called to see if it was raining.
there is a walkout on the backside and there is also a lot of rescaping of the land. The front of the house (to the left side of the hole) will be brought up almost 3 feet with dirt and fill to get to the new grade once the walls are set. That is where most of the height missing is coming from.
No work today due to rain, even though I told them yesterday they needed to work late to make sure they stayed on schedule for Thursday. When I dropped by the property yesterday afternoon at 1430 there was no one in sight.
Now I am being told that the walls won't go in till Monday most likely, which makes me ol so happy.
Needless to say someone got yelled at this morning, because the contractor didn't even show up on the job, he called to see if it was raining.
No work today due to rain, even though I told them yesterday they needed to work late to make sure they stayed on schedule for Thursday. When I dropped by the property yesterday afternoon at 1430 there was no one in sight.
Now I am being told that the walls won't go in till Monday most likely, which makes me ol so happy.
Needless to say someone got yelled at this morning, because the contractor didn't even show up on the job, he called to see if it was raining.



h: